A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
Step by step video & image solution for A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work? by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.
Topper's Solved these Questions
- BOOK - NCERT EXEMPLARCHAPTER - DIRECT AND INVERSE PROPORTIONS EXERCISE - THINK AND DISCUSS2videos
DIRECT AND INVERSE PROPORTIONS
- BOOK - NCERT EXEMPLARCHAPTER - DIRECT AND INVERSE PROPORTIONS EXERCISE - THINK AND DISCUSS2videos
DIRECT AND INVERSE PROPORTIONS
- BOOK - NCERT EXEMPLARCHAPTER - DATA HANDLINGEXERCISE - EXERCISE73videos
DATA HANDLING
- BOOK - NCERT EXEMPLARCHAPTER - EXPONENTS AND POWERSEXERCISE - EXERCISE195videos
EXPONENTS AND POWERS
Similar Questions
Knowledge Check
- Question 1 - Select One
A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
A100B60C75DNone of these - Question 2 - Select One
A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
A70B75C80D85 - Question 3 - Select One
25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?
A120B125C100D215
An employer has a workforce of 300 employees to finish a project in 8 months.How many extra employees should he employ to complete the project in 6 months?
View SolutionTwelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?
View SolutionTwelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?
View SolutionA work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
View SolutionA contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?View Solution