Doubtnut Promotions Sticky

A contract on construction job specifies a penalty for delay of completion beyond a certain date is as follows,
₹200 for 1st day,250 for 2nd day,300 for 3rd day and so on.If the contractor pays 27,750 as penalty,find the number of days for which the work is delayed.
Solution in Assamese

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for A contract on construction job specifies a penalty for delay of completion beyond a certain date is as follows, ₹200 for 1st day,₹250 for 2nd day,₹300 for 3rd day and so on.If the contractor pays 27,750 as penalty,find the number of days for which the work is delayed. by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.

Updated on:21/07/2023

Related Playlists


Similar Questions