Doubtnut Promotions Sticky

A, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of the work. In how many days will the work be completed ? 15 days b. 22 days c. 25  days d. 35 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

LCM of 24,36 and 48 is 144.
so let the work be of eating 144 chocolates.
A eats 6 chocolates per day, B eats 4 chocolates per day and C eats 3 chocolates per day.
Together they will eat 13 chocolates per day.
they worked for 4 days together so they ate=13 x4=52 chocolates
Number of chocolates left=144-52=92
A left 3 days before completion so B had to work alone, so he ate =3x4=12chocolates alone
number of chocolates left =92-12=80 chocolates
A and B eat 10 chocolates together so tehy took 8 days when they were together.
THus the work will be completed in=4+8+3=15 days.

|
Updated on:21/07/2023

Related Playlists


Similar Questions