Doubtnut Promotions Sticky

A and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?

A

28

B

36

C

40

D

32

Text Solution
Verified by Experts

The correct Answer is:(c)


Let the A can do the task in x days.
1x+110=18 ltbgt 1x=18110+10880=280=140
x=40
Alternate Solution:
If total work = 80 units
Then in 1 day (A+B) will do 8010=10 unit of work
A does 2 unit of work each day
A requires 802=40 days to complete work

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Related Playlists


Similar Questions