56 workers canfinish a piece of work in 14 days. If the work
is to be completed in 8 days, then how many extra workers
are required ?
36
48
44
42
The correct Answer is:(d)
Here, M1=56,D1=14,M2=?,D2=8
M1D1=M2D2
56×14=M2×8
⇒M2=98
Hence, extra workers to be required
=98−56=42
Related Playlists
Similar Questions
56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
View Solution42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
View SolutionIn a field 6 workers complete a task in 16 days.If this task is to be completed in 4 days,then how many workers will be required?
View SolutionA can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?
View SolutionIf 56 men can do a piece of work in 42 days. How many men will do it in 14 days?
View SolutionIf 56 men can do a piece of work in 42 days. How many men will do it in 14 days?
View SolutionA can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?
View SolutionA can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
View Solution