Doubtnut Promotions Sticky

240 men can finish a work in 20 days working 5 hours a day. To finish the work within 10 days working 8 hours a day, the minimum number of men required is
240 आदमी प्रतिदिन 5 घंटे काम करके एक काम को 20 दिन में पूरा कर सकते है। उसी काम को प्रतिदिन 8 घंटे काम करके 10 दिन के भीतर पूरा करने के लिए अपेक्षित आदमियों की न्यूनतम संख्या है-

A

310

B

300

C

313

D

312

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to determine the minimum number of men required to complete the work in a specified time and with a different working hour per day.

1. Understand the Given Information:
- 240 men can finish the work in 20 days working 5 hours a day.
- We need to find out how many men (let's denote this as P2) are required to finish the same work in 10 days working 8 hours a day.

2. Calculate the Total Work Done:
- The total work can be calculated using the formula:
Total Work=Number of Men×Number of Days×Hours per Day
- For the first scenario:
Total Work=240 men×20 days×5 hours/day=240×20×5=24000 man-hours

3. Set Up the Equation for the New Scenario:
- In the new scenario, we want to finish the same total work (24000 man-hours) in 10 days working 8 hours a day:
Total Work=P2×10 days×8 hours/day
- This gives us the equation:
24000=P2×10×8

4. Solve for P2:
- Rearranging the equation to solve for P2:
P2=2400010×8=2400080=300

5. Conclusion:
- Therefore, the minimum number of men required to finish the work in 10 days working 8 hours a day is 300 men.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:

    Aa. 30
    Bb. 32
    Cc. 34
    Dd. 36
  • Question 2 - Select One

    If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?

    A52
    B31
    C13
    D65
  • Question 3 - Select One

    If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?

    A15521 days
    B1123 days
    C6916 days
    D415 days