2 men each working 5 hour per day can finish a job in 12 days. How long will 4 men each working 2 hours per day take to finish the same job?
let the number of days be x.
The ratio of number of days=12:x
Number of days it takes is inversely proportional to the number of hours each man works per day and the number of men at work.
тИ┤12:x=4├Ч2:2├Ч5
тЗТ12x=810тЗТx=10├Ч128=15 days
тИ┤ 4 men each working 2 hours per day can finish the job in 15 days.
Similar Questions
2 men each working 5 hour per day can finish a job in 12 days. How long will 4 men each working 2 hours per day take to finish the same job?
View Solution4 men, each working 6 hours per day can build a wall in 9 days. How long will 6 men, each working 3 hours per day take to finish the same work?
View SolutionIf 9 men working 712 hours a day can finish a piece of work in 20 days, then how many days will be taken by 12 men, working 6 hours a day to finish the work? It is being given that 2 men of latter type work as much as 3 men of the former type. 11 b. 13 c. 912 d. 1212
View Solution10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
View Solution3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work?
View Solution24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:
View SolutionIf 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
View SolutionIf 9 men working 712 hours a day can finish a piece of work in 20 days, then how many days will be taken by 12 men, working 6 hours a day to finish the work? It is being given that 2 men of latter type work as much as 3 men of the former type. 11 b. 13 c. 912 d. 1212
View SolutionA person invests money in two different schemes for 5 years and 8 years at 12% and 10% simple interest, respectively. At the completion of each scheme he gets the same interest. The ratio of his investments is
View SolutionA man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete. It in 4 days?
View Solution