Doubtnut Promotions Sticky

2 men and 5 boys together can finish a piece of work in 4 days, while 3 men and 6 boys can finish it in 3 days. Find the time taken by 1 man alone to finish the work and than taken by 1 boy alone.

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:1 man finish in 18 days and 1 boy in 36 days.


To solve the problem, we will set up equations based on the information given and then solve for the time taken by one man and one boy to finish the work alone.

Step 1: Define Variables
Let:
- X = time taken by 1 man to finish the work (in days)
- Y = time taken by 1 boy to finish the work (in days)

Step 2: Set Up the Equations
From the problem, we know:
1. 2 men and 5 boys can finish the work in 4 days.
2. 3 men and 6 boys can finish the work in 3 days.

Using the work formula (Work = Rate × Time), we can express the work done in terms of X and Y.

Equation 1:
The work done by 2 men and 5 boys in 4 days:
2X+5Y=14

Equation 2:
The work done by 3 men and 6 boys in 3 days:
3X+6Y=13

Step 3: Clear the Fractions
To eliminate the fractions, we can multiply through by the least common multiple (LCM) of the denominators.

For Equation 1:
Multiply through by 4XY:
4Y(2)+4X(5)=XY
8Y+20X=XY(Equation 1)

For Equation 2:
Multiply through by 3XY:
3Y(3)+3X(6)=XY
9Y+18X=XY(Equation 2)

Step 4: Rearranging the Equations
Rearranging both equations gives:
1. XY8Y20X=0 (Equation 1)
2. XY9Y18X=0 (Equation 2)

Step 5: Subtract the Equations
Now, subtract Equation 1 from Equation 2:
(XY9Y18X)(XY8Y20X)=0
This simplifies to:
9Y+8Y18X+20X=0
Y+2X=0
Thus, we have:
Y=2X(Equation 3)

Step 6: Substitute Back
Now substitute Y=2X into either Equation 1 or Equation 2. Let's use Equation 1:
XY8Y20X=0
Substituting Y:
X(2X)8(2X)20X=0
2X216X20X=0
2X236X=0
Factoring out 2X:
2X(X18)=0
Thus, X=0 or X=18. Since X cannot be zero, we have:
X=18

Step 7: Find Y
Using Equation 3:
Y=2X=2(18)=36

Conclusion
The time taken by 1 man alone to finish the work is 18 days, and the time taken by 1 boy alone to finish the work is 36 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    X and Y together can finish a piece of work in 15 days, while Y alone can finish it in 40 days. X alone can finish the work in:

    A24 days
    B26 days
    C25 days
    D23 days
  • Question 2 - Select One

    A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in

    A15 days
    B18 days
    C20 days
    D25 days