Doubtnut Promotions Sticky

150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:25 hours


Suppose that the work completed in n days
Total number of workers engaged for 1 day each
= 150 +146 +142 +…… to n terms
n2×[2×150+(n1)×(4)]=n=n(1522n)
If 150 workers are engaged each day, time take= (n-8) days.
Number of workers engaged of 1 day = 150 (n-8)
n(152 - 2n) = 150 ( n-8) n2n600=0
(n25)(n+24)=0
n=25 [,n24]

|
Updated on:21/07/2023

Related Playlists


Similar Questions