Doubtnut Promotions Sticky

15 men take 42 days of 4 hours each to do piece of work. How many days of 6 hours each would 21 women take if 3 women do as much work as 2 men?

A

15

B

22

C

25

D

30

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's break down the information given and find the solution.

Step 1: Calculate the total work done by men
We know that:
- 15 men take 42 days, working 4 hours each day.

First, we calculate the total hours worked by 15 men:
Total hours=Number of men×Number of days×Hours per day
Total hours=15×42×4
Total hours=2520 hours

Step 2: Calculate the work done in terms of efficiency
Let’s define the work done as 1 unit. The total work done by 15 men in 2520 hours can be expressed in terms of their efficiency:
Efficiency of 15 men=1 unit2520 hours=12520 units per hour

Step 3: Calculate the efficiency of one man
The efficiency of one man can be calculated as:
Efficiency of 1 man=115×12520=137800 units per hour

Step 4: Relate women’s efficiency to men’s efficiency
We are given that 3 women do as much work as 2 men. Therefore, the efficiency ratio of women to men is:
Efficiency of womenEfficiency of men=23

Let the efficiency of one man be 3k and the efficiency of one woman be 2k.

Step 5: Calculate the total efficiency of 21 women
The total efficiency of 21 women is:
Total efficiency of 21 women=21×2k=42k

Step 6: Set up the equation for work done
Now we can set up the equation for the work done:
Total work done by 15 men=Total work done by 21 women
2520 hours=142k×Total hours worked by women

Step 7: Calculate the total hours worked by women
Let x be the number of days taken by 21 women working 6 hours each day:
Total hours worked by women=6x
So we have:
2520=42k×6x

Step 8: Solve for x
We can simplify:
2520=252k×x
Dividing both sides by 252k:
x=2520252=10 days

Step 9: Convert days to hours
Since the women work 6 hours each day, we need to find out how many days it takes:
Total days=Totalhours6=25206=420 hours

Final Calculation
Now we need to find out how many days of 6 hours each would be required:
Days=4206=70 days

Conclusion
Thus, 21 women would take 70 days of 6 hours each to complete the work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 men take 42 days of 4 hours each to do a piece of work. How many days of 6 hours each would 21 women take if 3 women do as much work as 2 men?

    A15
    B22
    C25
    D30
  • Question 2 - Select One

    15 men take 21 days of 8 hours each to do a piece of work How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men? 18 b.  20 c. 25 d. 30

    A20
    B25
    C18
    D30
  • Question 3 - Select One

    34 men can do a piece of work in 12 days . How many days will 51 men take to do it

    Aa) 8
    Bb) 5
    Cc) 10
    Dd) 6