A and B working together can complete 45% of a work in 18 days. A alone can complete the same work in 60 days. A and B work together for 16 days, and then A leaves. B alone will complete the remaining work in
80 days
60 days
72 days
75 days
The correct Answer is:C
To solve the problem step by step, we will first determine the work rates of A and B, and then find out how long B will take to complete the remaining work after A leaves.
Step 1: Determine the work rate of A and B together
A and B together can complete 45% of the work in 18 days.
To find their combined work rate:
- Work completed in 18 days = 45% of the work
- Therefore, in 1 day, A and B together complete:
Work rate of A and B=45%18=0.4518=0.025 (work per day)
Step 2: Determine the work rate of A alone
A can complete the entire work in 60 days.
Thus, A's work rate is:
Work rate of A=100%60=160 (work per day)
Step 3: Determine the work rate of B
Let the work rate of B be b.
From the combined work rate of A and B:
Work rate of A+Work rate of B=Work rate of A and B
160+b=0.025
To find b:
b=0.025−160
Convert 160 to a decimal:
160≈0.01667
So,
b=0.025−0.01667=0.00833 (work per day)
Step 4: Calculate the total work
Since A and B together can complete 100% of the work in:
Total work=1Work rate of A and B=10.025=40 days
Step 5: Calculate the work done by A and B in 16 days
In 16 days, A and B together will complete:
Work done in 16 days=16×0.025=0.4 (or 40% of the work)
Step 6: Calculate the remaining work
The remaining work after 16 days is:
Remaining work=100%−40%=60%
Step 7: Calculate how long B will take to complete the remaining work
B's work rate is 0.00833 (work per day). To find the time t taken by B to complete the remaining 60% of the work:
t=Remaining workWork rate of B=0.60.00833≈72 days
Final Answer
B alone will complete the remaining work in approximately 72 days.
---
A and B together can complete 45% of the work in 18 days.
- Work completed in 18 days = 45% of the work
- Therefore, in 1 day, A and B together complete:
Work rate of A and B=45%18=0.4518=0.025 (work per day)
A can complete the entire work in 60 days.
Work rate of A=100%60=160 (work per day)
Let the work rate of B be b.
Work rate of A+Work rate of B=Work rate of A and B
160+b=0.025
b=0.025−160
Convert 160 to a decimal:
160≈0.01667
So,
b=0.025−0.01667=0.00833 (work per day)
Since A and B together can complete 100% of the work in:
Total work=1Work rate of A and B=10.025=40 days
In 16 days, A and B together will complete:
Work done in 16 days=16×0.025=0.4 (or 40% of the work)
The remaining work after 16 days is:
Remaining work=100%−40%=60%
B's work rate is 0.00833 (work per day). To find the time t taken by B to complete the remaining 60% of the work:
t=Remaining workWork rate of B=0.60.00833≈72 days
B alone will complete the remaining work in approximately 72 days.
Similar Questions
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View SolutionA can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
View Solution
Knowledge Check
A is as efficient as B and C together. Working together A and B can complete a work in 36 days and C alone can complete it in 60 days. A and C work together for 10 days. B alone will complete the remaining work in :
A की कार्य क्षमता B और C की कुल कार्य क्षमता के बराबर है | एक साथ कार्य करते हुए, A और B किसी कार्य को 36 दिनों में कर सकते हैं तथा C अकेले इस कार्य को 60 दिनों में कर सकता है | A और C 10 दिनों तक एक साथ कार्य करते हैं | B अकेले शेष कार्य कितने दिनों में समाप्त करेगा ?A110 daysB88 daysC84 daysD90 daysA can complete 3313% of a work in 5 days and B can complete 40% of the same work in 10 days. They work together for 5 days and then B left the work. A alone will complete the remaining work in:
A712 daysB5 daysC7 daysD512 daysA can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in
A6 daysB4 daysC8 daysD9 days
A can do 35th of a work in 12 days, B can do 13rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?
View SolutionA can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
View SolutionA and B together can complete a work in 8 days . B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionA and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?
View Solution