A and B working together can complete 45% of a work in 18 days. A alone can complete the same work in 60 days. A and B work together for 16 days, and then A leaves. B alone will complete the remaining work in

A

80 days

B

60 days

C

72 days

D

75 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first determine the work rates of A and B, and then find out how long B will take to complete the remaining work after A leaves.

Step 1: Determine the work rate of A and B together
A and B together can complete 45% of the work in 18 days.

To find their combined work rate:
- Work completed in 18 days = 45% of the work
- Therefore, in 1 day, A and B together complete:
Work rate of A and B=45%18=0.4518=0.025 (work per day)

Step 2: Determine the work rate of A alone
A can complete the entire work in 60 days.

Thus, A's work rate is:
Work rate of A=100%60=160 (work per day)

Step 3: Determine the work rate of B
Let the work rate of B be b.

From the combined work rate of A and B:
Work rate of A+Work rate of B=Work rate of A and B
160+b=0.025

To find b:
b=0.025160
Convert 160 to a decimal:
1600.01667
So,
b=0.0250.01667=0.00833 (work per day)

Step 4: Calculate the total work
Since A and B together can complete 100% of the work in:
Total work=1Work rate of A and B=10.025=40 days

Step 5: Calculate the work done by A and B in 16 days
In 16 days, A and B together will complete:
Work done in 16 days=16×0.025=0.4 (or 40% of the work)

Step 6: Calculate the remaining work
The remaining work after 16 days is:
Remaining work=100%40%=60%

Step 7: Calculate how long B will take to complete the remaining work
B's work rate is 0.00833 (work per day). To find the time t taken by B to complete the remaining 60% of the work:
t=Remaining workWork rate of B=0.60.0083372 days

Final Answer
B alone will complete the remaining work in approximately 72 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A is as efficient as B and C together. Working together A and B can complete a work in 36 days and C alone can complete it in 60 days. A and C work together for 10 days. B alone will complete the remaining work in :
    A की कार्य क्षमता B और C की कुल कार्य क्षमता के बराबर है | एक साथ कार्य करते हुए, A और B किसी कार्य को 36 दिनों में कर सकते हैं तथा C अकेले इस कार्य को 60 दिनों में कर सकता है | A और C 10 दिनों तक एक साथ कार्य करते हैं | B अकेले शेष कार्य कितने दिनों में समाप्त करेगा ?

    A110 days
    B88 days
    C84 days
    D90 days
  • A can complete 3313% of a work in 5 days and B can complete 40% of the same work in 10 days. They work together for 5 days and then B left the work. A alone will complete the remaining work in:

    A712 days
    B5 days
    C7 days
    D512 days
  • A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

    A6 days
    B4 days
    C8 days
    D9 days