12 men can complete a painting work in 8 days. However, 16 women can complete the same painting work in 12 days 8 men started painting the house. After 6 days of painting. 2 men were replaced by 4 women. Now how many days will they take to complete the remaining painting?
4
6
8
5
The correct Answer is:B
To solve the problem step by step, we will first calculate the total work done in terms of "man-days" and "woman-days," then determine how much work has been completed, and finally find out how many more days are needed to finish the remaining work.
Step 1: Calculate the total work in man-days
12 men can complete the painting work in 8 days. Therefore, the total work can be calculated as:
Total work=Number of men×Number of days=12 men×8 days=96 man-days
Step 2: Calculate the work done by 8 men in 6 days
Now, we need to find out how much work 8 men can do in 6 days:
Work done by 8 men in 6 days=8 men×6 days=48 man-days
Step 3: Calculate the remaining work
Now, we subtract the work done from the total work:
Remaining work=Total work−Work done=96 man-days−48 man-days=48 man-days
Step 4: Calculate the work rate after replacing 2 men with 4 women
After 6 days, 2 men are replaced by 4 women. Now we have:
- 6 men remaining
- 4 women added
First, we need to find the work rate of 1 woman. We know that 16 women can complete the work in 12 days:
Total work in woman-days=16 women×12 days=192 woman-days
Thus, the work done by 1 woman in 1 day is:
Work rate of 1 woman=192 woman-days16 women×12 days=192192=1 man-day
This means that 1 woman does 116 of the work done by 1 man in a day.
Now, we can find the work done by 6 men and 4 women in one day:
- Work done by 6 men in one day:
6 men=6 man-days
- Work done by 4 women in one day:
4 women=4×116 man-days=416=14 man-days
Thus, the total work done by 6 men and 4 women in one day is:
Total work per day=6+14=6.25 man-days
Step 5: Calculate the number of days to complete the remaining work
Now, we need to find out how many days it will take to complete the remaining 48 man-days of work:
Days required=Remaining workTotal work per day=48 man-days6.25 man-days/day=7.68 days
Since we typically round up in such scenarios, we can say it will take approximately 8 days to complete the remaining work.
Final Answer
Thus, the total number of days required to complete the remaining painting work after the changes is approximately 8 days.
12 men can complete the painting work in 8 days. Therefore, the total work can be calculated as:
Total work=Number of men×Number of days=12 men×8 days=96 man-days
Now, we need to find out how much work 8 men can do in 6 days:
Work done by 8 men in 6 days=8 men×6 days=48 man-days
Now, we subtract the work done from the total work:
Remaining work=Total work−Work done=96 man-days−48 man-days=48 man-days
After 6 days, 2 men are replaced by 4 women. Now we have:
- 6 men remaining
- 4 women added
Total work in woman-days=16 women×12 days=192 woman-days
Thus, the work done by 1 woman in 1 day is:
Work rate of 1 woman=192 woman-days16 women×12 days=192192=1 man-day
This means that 1 woman does 116 of the work done by 1 man in a day.
- Work done by 6 men in one day:
6 men=6 man-days
- Work done by 4 women in one day:
4 women=4×116 man-days=416=14 man-days
Thus, the total work done by 6 men and 4 women in one day is:
Total work per day=6+14=6.25 man-days
Now, we need to find out how many days it will take to complete the remaining 48 man-days of work:
Days required=Remaining workTotal work per day=48 man-days6.25 man-days/day=7.68 days
Since we typically round up in such scenarios, we can say it will take approximately 8 days to complete the remaining work.
Thus, the total number of days required to complete the remaining painting work after the changes is approximately 8 days.
Similar Questions
Knowledge Check
15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D3212 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?
A60 daysB45 daysC54 daysD48 days12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?
A16B12C18D10
12 Men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?
View Solution12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?
View Solution7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution