X and Y can complete a certain work in 16 days and 24 days , respectively. The work together for 4 days. Z alone completes the remaining work in 1012 days. Y and Z together can complete 78th part of the same work in :
10 days
8 days
9 days
12 days
The correct Answer is:C
To solve the problem step by step, we will first determine the work rates of X, Y, and Z, and then find out how long Y and Z will take to complete 78 of the work together.
Step 1: Determine the work rates of X and Y
- X can complete the work in 16 days, so the work done by X in one day is:
Work rate of X=116 (work/day)
- Y can complete the work in 24 days, so the work done by Y in one day is:
Work rate of Y=124 (work/day)
Step 2: Calculate the combined work rate of X and Y
- The combined work rate of X and Y when they work together is:
Combined work rate=116+124
- To add these fractions, we find a common denominator, which is 48:
116=348,124=248
- Therefore,
Combined work rate=348+248=548 (work/day)
Step 3: Calculate the work done by X and Y in 4 days
- In 4 days, the amount of work done by X and Y together is:
Work done in 4 days=4×548=2048=512
Step 4: Determine the remaining work
- The total work is considered as 1 unit. Therefore, the remaining work after X and Y have worked for 4 days is:
Remaining work=1−512=712
Step 5: Determine Z's work rate
- Z completes the remaining work in 1012 days, which is 212 days. Thus, Z's work rate is:
Work rate of Z=1212=221 (work/day)
Step 6: Calculate the work rate of Y and Z together
- The combined work rate of Y and Z is:
Work rate of Y and Z=124+221
- To add these fractions, we find a common denominator, which is 168:
124=7168,221=16168
- Therefore,
Combined work rate of Y and Z=7168+16168=23168 (work/day)
Step 7: Calculate the time taken by Y and Z to complete 78 of the work
- To find out how long it takes Y and Z to complete 78 of the work, we set up the equation:
Time=WorkWork rate=7823168=78×16823
- Simplifying this gives:
=7×2123=14723 days
Conclusion
Thus, Y and Z together can complete 78 of the work in 14723 days.
- X can complete the work in 16 days, so the work done by X in one day is:
Work rate of X=116 (work/day)
- Y can complete the work in 24 days, so the work done by Y in one day is:
Work rate of Y=124 (work/day)
- The combined work rate of X and Y when they work together is:
Combined work rate=116+124
- To add these fractions, we find a common denominator, which is 48:
116=348,124=248
- Therefore,
Combined work rate=348+248=548 (work/day)
- In 4 days, the amount of work done by X and Y together is:
Work done in 4 days=4×548=2048=512
- The total work is considered as 1 unit. Therefore, the remaining work after X and Y have worked for 4 days is:
Remaining work=1−512=712
- Z completes the remaining work in 1012 days, which is 212 days. Thus, Z's work rate is:
Work rate of Z=1212=221 (work/day)
- The combined work rate of Y and Z is:
Work rate of Y and Z=124+221
- To add these fractions, we find a common denominator, which is 168:
124=7168,221=16168
- Therefore,
Combined work rate of Y and Z=7168+16168=23168 (work/day)
- To find out how long it takes Y and Z to complete 78 of the work, we set up the equation:
Time=WorkWork rate=7823168=78×16823
- Simplifying this gives:
=7×2123=14723 days
Thus, Y and Z together can complete 78 of the work in 14723 days.
Similar Questions
A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
View SolutionA can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:
View Solution
Knowledge Check
- Question 1 - Select One
A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:
A8 daysB5 daysC4 daysD6 days - Question 2 - Select One
A and B can do a work in 6 days and 8 days respectively. Together they worked for 3 days and left. C complete the remaining work in 2 days. Find in how many days B and C together can complete 3/4th part of the total work.
A3B4C6D8 - Question 3 - Select One
X, Y and Z can complete a piece of work in 8, 20 and 25 days respectively. Working together, they will complete the same work in:
A18043 daysB16243 daysC20043 daysD17243 days
A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :
View SolutionX and Y can complete a work in 5 days. Y and Z can complete the same work in 6 days. Z and X can complete the same work in 152 days. In how many days will X, Y and Z together complete the work?
View SolutionA and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:
View SolutionWorking together A, B and C can complete a piece of work in 24 days. After working together for 4 days. C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:
View SolutionX alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work?
View Solution