A (working alone) can complete a task in 'x' days. A worked alone for 612 days and was then replaced by B and C who (working together) completed the remaining task in 3 days. Working alone, B and C take '0.5x' days and 8 days respectively to complete the entire task. What is the value of x?
8
24
20
16
The correct Answer is:C
To solve the problem, we will break it down step by step.
Step 1: Define the total work
Let's assume the total work is 1 unit.
Step 2: Calculate A's work rate
A can complete the entire task in 'x' days. Therefore, A's work rate is:
Work rate of A=1x units per day
Step 3: Calculate the work done by A in 6.5 days
A worked alone for 612 days, which is 6.5 days. The work done by A in this time is:
Work done by A=Work rate of A×Time=1x×6.5=6.5x units
Step 4: Calculate the remaining work
The remaining work after A has worked for 6.5 days is:
Remaining work=1−6.5x
Step 5: Calculate the work rate of B and C
B can complete the task in 0.5x days, so B's work rate is:
Work rate of B=10.5x=2x units per day
C can complete the task in 8 days, so C's work rate is:
Work rate of C=18 units per day
Step 6: Calculate the combined work rate of B and C
The combined work rate of B and C is:
Combined work rate of B and C=2x+18
Step 7: Calculate the work done by B and C in 3 days
B and C completed the remaining work in 3 days. The work done by B and C in this time is:
Work done by B and C=(2x+18)×3
Step 8: Set up the equation
Since the work done by B and C is equal to the remaining work, we can set up the equation:
(2x+18)×3=1−6.5x
Step 9: Simplify the equation
Distributing the 3 on the left side gives:
6x+38=1−6.5x
Now, let's combine like terms:
6x+6.5x=1−38
12.5x=1−38
Calculating 1−38:
1−38=88−38=58
So we have:
12.5x=58
Step 10: Solve for x
Cross-multiplying gives:
12.5×8=5x
100=5x
x=1005=20
Final Answer
The value of x is 20.
---
Let's assume the total work is 1 unit.
A can complete the entire task in 'x' days. Therefore, A's work rate is:
Work rate of A=1x units per day
A worked alone for 612 days, which is 6.5 days. The work done by A in this time is:
Work done by A=Work rate of A×Time=1x×6.5=6.5x units
The remaining work after A has worked for 6.5 days is:
Remaining work=1−6.5x
B can complete the task in 0.5x days, so B's work rate is:
Work rate of B=10.5x=2x units per day
C can complete the task in 8 days, so C's work rate is:
Work rate of C=18 units per day
The combined work rate of B and C is:
Combined work rate of B and C=2x+18
B and C completed the remaining work in 3 days. The work done by B and C in this time is:
Work done by B and C=(2x+18)×3
Since the work done by B and C is equal to the remaining work, we can set up the equation:
(2x+18)×3=1−6.5x
Distributing the 3 on the left side gives:
6x+38=1−6.5x
Now, let's combine like terms:
6x+6.5x=1−38
12.5x=1−38
Calculating 1−38:
1−38=88−38=58
So we have:
12.5x=58
Cross-multiplying gives:
12.5×8=5x
100=5x
x=1005=20
The value of x is 20.
Similar Questions
A alone can complete a task in 3 days. B alone can complete the same task in 7 days If A and B work together for 2 days, what fraction of the task will be left?
View SolutionA and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?
View Solution
Knowledge Check
A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days . In how many days can C working alone complete the work ?
A12B68C72D90A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
A6 daysB4 daysC10 daysD8 daysA and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?A28B36C40D32
A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
View SolutionWorking together A, B and C can complete a task in 12 days. A and B can do the task in 55 days and 66 days respectively if they worked alone. In how many days can C do the task if he worked alone?
View SolutionA alone can complete a task in 3 days and B alone can complete the same task in 6 days. In how manny days can A and B complete it together?
View SolutionA alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?
View SolutionA completes a work in 15 days. B completes the same work in 20 days. A started working alone after 1 day B joined him. How many days will they now take together to complete the remaining work ?
View Solution