Working together A and B complete a task in (7)1/2 days B alone takes 8 days less than A alone to complete the task if C alone takes 14 days to complete the same work what is difference between number of days taken by B alone and C alone to complete the task
5
1
4
2
The correct Answer is:D
To solve the problem, we need to find the difference between the number of days taken by B alone and C alone to complete the task. Let's break it down step by step.
Step 1: Understand the given information
- A and B together complete a task in 712 days.
- B alone takes 8 days less than A alone to complete the task.
- C alone takes 14 days to complete the same work.
Step 2: Convert mixed fraction to improper fraction
Convert 712 days into an improper fraction:
712=152 days
Step 3: Define variables for A and B
Let X be the number of days A takes to complete the task alone. Then, B takes:
X−8 days
Step 4: Calculate the work done in one day
The work done by A in one day is:
1X (work per day)
The work done by B in one day is:
1X−8 (work per day)
The combined work done by A and B in one day is:
1X+1X−8
Step 5: Set up the equation for combined work
Since A and B together complete the work in 152 days, their combined work per day is:
1152=215
Thus, we can set up the equation:
1X+1X−8=215
Step 6: Solve the equation
To solve the equation, find a common denominator:
(X−8)+XX(X−8)=215
This simplifies to:
2X−8X(X−8)=215
Cross-multiplying gives:
15(2X−8)=2X2−16X
Expanding and rearranging:
30X−120=2X2−16X
2X2−46X+120=0
Dividing the entire equation by 2:
X2−23X+60=0
Step 7: Factor the quadratic equation
To factor:
(X−20)(X−3)=0
Thus, X=20 or X=3. Since A cannot complete the work in 3 days (as they work together for longer), we take:
X=20 days for A
Step 8: Calculate days taken by B
Now, substituting back to find B's time:
B=X−8=20−8=12 days
Step 9: Days taken by C
We know C takes:
C=14 days
Step 10: Find the difference between B and C
The difference in days taken by B and C is:
|C−B|=|14−12|=2 days
Final Answer
The difference between the number of days taken by B alone and C alone to complete the task is:
2
- A and B together complete a task in 712 days.
- B alone takes 8 days less than A alone to complete the task.
- C alone takes 14 days to complete the same work.
Convert 712 days into an improper fraction:
712=152 days
Let X be the number of days A takes to complete the task alone. Then, B takes:
X−8 days
The work done by A in one day is:
1X (work per day)
The work done by B in one day is:
1X−8 (work per day)
The combined work done by A and B in one day is:
1X+1X−8
Since A and B together complete the work in 152 days, their combined work per day is:
1152=215
Thus, we can set up the equation:
1X+1X−8=215
To solve the equation, find a common denominator:
(X−8)+XX(X−8)=215
This simplifies to:
2X−8X(X−8)=215
Cross-multiplying gives:
15(2X−8)=2X2−16X
Expanding and rearranging:
30X−120=2X2−16X
2X2−46X+120=0
Dividing the entire equation by 2:
X2−23X+60=0
To factor:
(X−20)(X−3)=0
Thus, X=20 or X=3. Since A cannot complete the work in 3 days (as they work together for longer), we take:
X=20 days for A
Now, substituting back to find B's time:
B=X−8=20−8=12 days
We know C takes:
C=14 days
The difference in days taken by B and C is:
|C−B|=|14−12|=2 days
The difference between the number of days taken by B alone and C alone to complete the task is:
2
Similar Questions
A and B on working together can complete a work in 4 days. A alone takes 6 days less than B alone takes. In how many days C alone can complete the work if he is 50% more efficient than B?
View SolutionA and B can complete a task in 30 days, whereas A,B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can together complete a tsk in 21 days. If a alone takes 42 days to complete the task, the number of days that B would take to do the task alone is :
A42B36C27D32 - Question 2 - Select One
A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
A6 daysB4 daysC10 daysD8 days - Question 3 - Select One
A alone can complete a task in 3 days and B alone can complete the same task in 6 days. In how manny days can A and B complete it together?
A2B6C1D3
A and B can complete a task in 30 days, whereas A. B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View SolutionIf A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
View SolutionC alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
View SolutionP and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?
View Solution