Two workers A and B manufactured a batch of identical parts. A worked for 2 hours and B worked for 5 hours and they completed half the job. Then they worked together for another 3 hours and they had to do (1/20)th of the job. How many hours time does B take to complete the job, if he worked alone?
24
12
15
30
The correct Answer is:C
To solve the problem step by step, let's denote the time taken by worker A to complete the job alone as A hours and the time taken by worker B to complete the job alone as B hours.
Step 1: Determine the work done by A and B in the first part.
A worked for 2 hours and B worked for 5 hours, completing half the job.
The work done by A in 2 hours is:
Work done by A=2A
The work done by B in 5 hours is:
Work done by B=5B
Since they completed half the job together:
2A+5B=12
Step 2: Rearranging the equation.
Multiply the entire equation by 2AB to eliminate the denominators:
2B⋅2+5A⋅2=AB
This simplifies to:
4B+10A=AB(Equation 1)
Step 3: Determine the work done when A and B worked together for 3 hours.
Now, A and B worked together for 3 hours and had 120 of the job left.
The work done by A in 3 hours is:
Work done by A=3A
The work done by B in 3 hours is:
Work done by B=3B
The total work done in these 3 hours is:
3A+3B=120
Step 4: Rearranging the second equation.
Multiply the entire equation by 20AB:
20B⋅3+20A⋅3=AB
This simplifies to:
60B+60A=AB(Equation 2)
Step 5: Solve the equations simultaneously.
Now we have two equations:
1. AB−4B−10A=0
2. AB−60B−60A=0
We can set these equal to each other:
4B+10A=60B+60A
Rearranging gives:
60B−4B=60A−10A
This simplifies to:
56B=50A
Thus:
AB=5650=2825
This implies:
A=2825B
Step 6: Substitute A back into one of the equations.
Substituting A into Equation 1:
4B+10(2825B)=B(2825B)
This simplifies to:
4B+28025B=2825B2
Multiplying through by 25 to eliminate the fraction:
100B+280B=28B2
This simplifies to:
380B=28B2
Rearranging gives:
28B2−380B=0
Factoring out B:
B(28B−380)=0
Thus:
B=0orB=38028=13.57 hours (approximately)
Final Answer:
Since we are looking for the time taken by B to complete the job alone, we round it to the nearest whole number:
B≈15 hours
A worked for 2 hours and B worked for 5 hours, completing half the job.
Work done by A=2A
Work done by B=5B
2A+5B=12
Multiply the entire equation by 2AB to eliminate the denominators:
2B⋅2+5A⋅2=AB
This simplifies to:
4B+10A=AB(Equation 1)
Now, A and B worked together for 3 hours and had 120 of the job left.
Work done by A=3A
Work done by B=3B
3A+3B=120
Multiply the entire equation by 20AB:
20B⋅3+20A⋅3=AB
This simplifies to:
60B+60A=AB(Equation 2)
Now we have two equations:
1. AB−4B−10A=0
2. AB−60B−60A=0
4B+10A=60B+60A
Rearranging gives:
60B−4B=60A−10A
This simplifies to:
56B=50A
Thus:
AB=5650=2825
This implies:
A=2825B
Substituting A into Equation 1:
4B+10(2825B)=B(2825B)
This simplifies to:
4B+28025B=2825B2
Multiplying through by 25 to eliminate the fraction:
100B+280B=28B2
This simplifies to:
380B=28B2
Rearranging gives:
28B2−380B=0
Factoring out B:
B(28B−380)=0
Thus:
B=0orB=38028=13.57 hours (approximately)
Since we are looking for the time taken by B to complete the job alone, we round it to the nearest whole number:
B≈15 hours
Similar Questions
Two workers A and B are engaged to do a piece of work.Working alone, A takes 8 hours more to complete the workthan if both worked together. On the other hand, workingalone, B would need 412 hours more to complete the work than if both worked together. How much time would they take tocomplete the job working together?
View SolutionA and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?
View Solution
Knowledge Check
A and B together can do a job in 15 days and A alone could do the same job in 20 days how many days would B take to do half the job if he worked alone
A60B30C45D4012 worker take 4 hours to complete a job.How long would it take 15 workers to complete the job?
A2 hrsB3.2 hrsC3 .5 hrsD3 hrsSuresh can complete a job in 15 hours Ashutosh alone can complete the same job in 10 hours. Suresh works for 9 hours and then the remaining job is completed by Ashutosh. How many hours will it take Ashutosh to complete the remaining job alone?
A4B5C6D12
A man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete. It in 4 days?
View SolutionTwo workers A and B are engaged to do a piece of work. Working alone, A takes 8 hours more to complete the work than if both worked together. On the other hand, working alone, B would need 412 hours more to complete the work than if both worked together. How much time would they take to complete the job working together?
View SolutionTwo workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take 412 hours more than when work together. The time required to finish the work together is
View SolutionA takes 5 hours more time than that taken by B to complete a work. If working together they can complete a work in 6 hours, then the number of hours that takes to complete the work individually is
View SolutionRobin can do a work in 10 hours. Pradeep and Robin together can do the same work in 4 hours. Pradeep and Nitin together can do the same work in 5 hours. In how many hours Nitin alone can complete the same work?
View Solution