24 men working 8 hours a day make a road in 15 days. In how many days 48 men working 6 hours a day will make the three times long road?
The correct Answer is:30 days
To solve the problem step by step, we will use the concept of work done, which is calculated as:
Work=Number of Men×Number of Days×Number of Hours per Day
Step 1: Calculate the total work done by the first group of men
Given:
- Number of men (P1) = 24
- Number of days (D1) = 15
- Number of hours per day (H1) = 8
Using the formula for work:
W1=P1×D1×H1=24×15×8
Calculating this:
W1=24×15=360
W1=360×8=2880 man-hours
Step 2: Calculate the total work for the new scenario
The new scenario involves making a road that is three times longer than the original road. Therefore, the total work required (W2) will be:
W2=3×W1=3×2880=8640 man-hours
Step 3: Set up the equation for the second group of men
Now we need to find out how many days (D2) it will take for 48 men working 6 hours a day to complete this work.
Given:
- Number of men (P2) = 48
- Number of hours per day (H2) = 6
Using the work formula again, we have:
W2=P2×D2×H2
Substituting the known values:
8640=48×D2×6
Step 4: Solve for D2
First, calculate 48×6:
48×6=288
Now substitute this back into the equation:
8640=288×D2
To find D2, divide both sides by 288:
D2=8640288
Calculating this gives:
D2=30
Final Answer
Thus, it will take 30 days for 48 men working 6 hours a day to make the three times long road.
---
Given:
- Number of men (P1) = 24
- Number of days (D1) = 15
- Number of hours per day (H1) = 8
W1=360×8=2880 man-hours
The new scenario involves making a road that is three times longer than the original road. Therefore, the total work required (W2) will be:
Now we need to find out how many days (D2) it will take for 48 men working 6 hours a day to complete this work.
- Number of men (P2) = 48
- Number of hours per day (H2) = 6
First, calculate 48×6:
Thus, it will take 30 days for 48 men working 6 hours a day to make the three times long road.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - SOLVED EXAMPLE10videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS15videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
If 30 men working 7 hours a day can make 12 tables in 18 days, how many days will 45 women working 9 hours a day take to make 32 chairs? Given, 4 men can make 3 tables in the same time as 3 women can make 4 chairs. a. 12 days b. 14 days C. 28 days d. 21 days
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View Solution
Knowledge Check
- Question 1 - Select One
10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
AA)40 daysBB)60 daysCC)50 daysDD)30 days - Question 2 - Select One
16 persons working 6 hours a day can complete a work in 10 days. In how many days 24 persons working 8 hours a day will complete 80% of that work?
एक दिन में 6 घंटे कार्य करके 16 व्यक्ति किसी कार्य को 10 दिनों में समाप्त कर सकते हैं | एक दिन में 8 घंटे कार्य करके 24 व्यक्ति इस कार्य का 80% भाग कितने दिनों में समाप्त कर सकते हैं ?A3B6C4D8 - Question 3 - Select One
30 men working 5 hours a day can do a task in 16 days in how many days will 40 men working 6 hours a day fo the same task ?
A. 12 days
B. 10 days
C. 15 days
D. 18 daysACBBCADD
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View SolutionTwelve men, working at 8 h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6 h a day can do the same work?
View SolutionTwelve men, working at 8h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6h a day can do the same work?
View SolutionIf 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?View Solution18 men or 36 boys working 6 hours a day can plough a field in 24 days. In how many days will 24 men and 24 boys working 9 hours a day plough the same field?
View Solution