30 men take 25 days to dig a pond. If the pond would have been dug in 15 days, then what is the number of men to be employed?
45
60
50
57
To solve the problem of how many men are required to dig a pond in 15 days, given that 30 men can do it in 25 days, we can use the concept of work done, which can be expressed in terms of men and days.
1. Identify the given values:
- Let M1=30 (the number of men initially)
- Let D1=25 (the number of days initially)
- Let D2=15 (the number of days we want to dig the pond in)
- Let M2 be the number of men required (this is what we need to find).
2. Use the work formula:
The total work done can be expressed as:
M1×D1=M2×D2
This equation states that the work done by the first group of men over the first period is equal to the work done by the second group of men over the second period.
3. Substitute the known values into the equation:
30×25=M2×15
4. Calculate the left side:
30×25=750
So, the equation now looks like:
750=M2×15
5. Solve for M2:
To find M2, divide both sides of the equation by 15:
M2=75015
6. Calculate M2:
M2=50
Conclusion:
The number of men required to dig the pond in 15 days is 50 men.
- Let M1=30 (the number of men initially)
- Let D1=25 (the number of days initially)
- Let D2=15 (the number of days we want to dig the pond in)
- Let M2 be the number of men required (this is what we need to find).
The total work done can be expressed as:
M1×D1=M2×D2
This equation states that the work done by the first group of men over the first period is equal to the work done by the second group of men over the second period.
30×25=M2×15
30×25=750
So, the equation now looks like:
750=M2×15
To find M2, divide both sides of the equation by 15:
M2=75015
M2=50
The number of men required to dig the pond in 15 days is 50 men.
Similar Questions
45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be :
View SolutionA certain number of men can do a piece of work in 40 days. If there were 45 men more the work could have been finished in 25 days. Find the original number of men employed in the work (A) 70 (B) 85 (C) 65 (D) 75
View Solution
Knowledge Check
- Question 1 - Select One
45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be
A50B54C60D72 - Question 2 - Select One
A contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .
A40B15C45D30 - Question 3 - Select One
Had been one men less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?
A14B9C6D8
12 men can dig a pond in 8 days. How many men can dig it in 6 days?
View SolutionA certain number of men completed a job in 10 days. If there 5 more men, it could have been completd in 8 days. How many men will be required to complete it ?
View SolutionIf 15 men take 21 days of 8 hours each to do a piece of work, then what is the number of days of 6 hours each that 21 women would take, if 3 women would do as much work as 2 men ?
View SolutionFifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.
View Solution18 men built a tanker in 25 days. How many days would it take for 10 men?
View Solution