30 men take 25 days to dig a pond. If the pond would have been dug in 15 days, then what is the number of men to be employed?

A

45

B

60

C

50

D

57

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem of how many men are required to dig a pond in 15 days, given that 30 men can do it in 25 days, we can use the concept of work done, which can be expressed in terms of men and days.

1. Identify the given values:
- Let M1=30 (the number of men initially)
- Let D1=25 (the number of days initially)
- Let D2=15 (the number of days we want to dig the pond in)
- Let M2 be the number of men required (this is what we need to find).

2. Use the work formula:
The total work done can be expressed as:
M1×D1=M2×D2
This equation states that the work done by the first group of men over the first period is equal to the work done by the second group of men over the second period.

3. Substitute the known values into the equation:
30×25=M2×15

4. Calculate the left side:
30×25=750
So, the equation now looks like:
750=M2×15

5. Solve for M2:
To find M2, divide both sides of the equation by 15:
M2=75015

6. Calculate M2:
M2=50

Conclusion:
The number of men required to dig the pond in 15 days is 50 men.

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be

    A50
    B54
    C60
    D72
  • Question 2 - Select One

    A contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .

    A40
    B15
    C45
    D30
  • Question 3 - Select One

    Had been one men less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?

    A14
    B9
    C6
    D8