Study the following information carefully and answer the given questions. Data below represent number of people required for various project to be completed in various days :
Study the following information carefully and answer the given questions. Data below represent number of people required for various project to be  completed in various days :        If in Team P, total number of workers = 0.5Z xx 2M,  then what is the number of days required by Team P to complete Project C?
If in Team P, total number of workers =0.5Z×2M, then what is the number of days required by Team P to complete Project C?

A

75 days

B

60 days

C

90 days

D

80 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C


Work unit of project C in both situation 1 and situation 2 are same
Z2×75=M2×108
Z2M2=10875=3625=6252
ZM=65
Total unit work of project C=36×75=2700
Days required by Team P to complete
Project C=2700(0.5Z×2M)=270030=90 days

Updated on:21/07/2023
|


Similar Questions


Knowledge Check

  • Study the following graph carefully and answer the questions given below it :-
    Number of people working in various departments of two different organisation:
    ocr_image
    What is the total number of people working in organisation B?

    A1925
    B1950
    C1975
    D1875
  • Study the following graph carefully and answer the questions given below
    ocr_image
    What was the percentage drop in the number of C type tyres manufactured from 2007 to 2008?

    A25%
    B10%
    C15%
    D2.5%
  • Study the following graph carefully to answer the questions given below.
    ocr_image
    What is the average number of Units produced by all the Companies together?

    A62513
    B63313
    C63323
    D62313