Rathin & Bratin together can complete a piece of work in 12 days. They start the work together but Rathin had to leave 7.5 days before the work got over. As a result it took a total of 15 days to complete the work. How many days would it have taken Bratin to complete the work by himself?
(a)20
(b)24
(c)30
(d)28
20
24
30
28
The correct Answer is:C
To solve the problem step by step, we will first determine the work done by Rathin and Bratin together, then find out how much work Bratin completed alone after Rathin left.
Step 1: Determine the work rate of Rathin and Bratin together
Rathin and Bratin together can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of Rathin and Bratin=112 work per day
Step 2: Calculate the total work done in 7.5 days
They work together for 7.5 days. The amount of work done by both in that time is:
Work done in 7.5 days=7.5×112=7.512=58 of the work
Step 3: Determine the remaining work
Since the total work is considered as 1, the remaining work after 7.5 days is:
Remaining work=1−58=38 of the work
Step 4: Calculate the time taken by Bratin to complete the remaining work
Bratin works alone for the remaining time, which is 15−7.5=7.5 days. We know that he completes 38 of the work in 7.5 days. Therefore, we can find Bratin's work rate:
Bratin's work rate=387.5=38×7.5=360=120 work per day
Step 5: Calculate how long it would take Bratin to complete the entire work alone
If Bratin can do 120 of the work in one day, then the total time taken by Bratin to complete the work alone is:
Time taken by Bratin=1120=20 days
Thus, the answer is that it would take Bratin 20 days to complete the work by himself.
Final Answer
(a) 20
Rathin and Bratin together can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of Rathin and Bratin=112 work per day
They work together for 7.5 days. The amount of work done by both in that time is:
Work done in 7.5 days=7.5×112=7.512=58 of the work
Since the total work is considered as 1, the remaining work after 7.5 days is:
Remaining work=1−58=38 of the work
Bratin works alone for the remaining time, which is 15−7.5=7.5 days. We know that he completes 38 of the work in 7.5 days. Therefore, we can find Bratin's work rate:
Bratin's work rate=387.5=38×7.5=360=120 work per day
If Bratin can do 120 of the work in one day, then the total time taken by Bratin to complete the work alone is:
Time taken by Bratin=1120=20 days
(a) 20
Similar Questions
A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is 635 b. 812 c. 1015 d. 1312
View Solution
Knowledge Check
Ratul and Pratul together can complete a task in 18 days. They start the task together, but Rahul had to leave 7 days before the work got over. As a result it took a total of 23 days to complete the task. How many days would it have taken Pratul to complete the work by himself?
A63B51C72D54A can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
A72 daysB64 daysC100 daysD120 daysA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these
A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionIf A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
View SolutionA can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?
View SolutionA can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
View SolutionA and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?
View Solution