Rathin & Bratin together can complete a piece of work in 12 days. They start the work together but Rathin had to leave 7.5 days before the work got over. As a result it took a total of 15 days to complete the work. How many days would it have taken Bratin to complete the work by himself?
(a)20
(b)24
(c)30
(d)28

A

20

B

24

C

30

D

28

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first determine the work done by Rathin and Bratin together, then find out how much work Bratin completed alone after Rathin left.

Step 1: Determine the work rate of Rathin and Bratin together
Rathin and Bratin together can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of Rathin and Bratin=112 work per day

Step 2: Calculate the total work done in 7.5 days
They work together for 7.5 days. The amount of work done by both in that time is:
Work done in 7.5 days=7.5×112=7.512=58 of the work

Step 3: Determine the remaining work
Since the total work is considered as 1, the remaining work after 7.5 days is:
Remaining work=158=38 of the work

Step 4: Calculate the time taken by Bratin to complete the remaining work
Bratin works alone for the remaining time, which is 157.5=7.5 days. We know that he completes 38 of the work in 7.5 days. Therefore, we can find Bratin's work rate:
Bratin's work rate=387.5=38×7.5=360=120 work per day

Step 5: Calculate how long it would take Bratin to complete the entire work alone
If Bratin can do 120 of the work in one day, then the total time taken by Bratin to complete the work alone is:
Time taken by Bratin=1120=20 days

Thus, the answer is that it would take Bratin 20 days to complete the work by himself.

Final Answer
(a) 20

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • Ratul and Pratul together can complete a task in 18 days. They start the task together, but Rahul had to leave 7 days before the work got over. As a result it took a total of 23 days to complete the task. How many days would it have taken Pratul to complete the work by himself?

    A63
    B51
    C72
    D54
  • A can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?

    A72 days
    B64 days
    C100 days
    D120 days
  • A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these