35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is
20
35
30
25
The correct Answer is:D
Step by step video & text solution for 35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Similar Questions
Knowledge Check
14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
A12 daysB7 daysC9 daysDNone of these25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?
A120B125C100D215A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 15th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?
A25B50C75Dcan't be determined
If 20 persons can do a piece of work in 7 days then calculate the number of persons required to complete the work in 28 days
View SolutionA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View SolutionIf 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
View SolutionIf 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View Solution