The ratio of efficiencies of A , B and C is 7 : 5 : 8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining was completed by A alone. The whole work was completed in :
A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 8 है | एक साथ कार्य करते हुए, वे किसी कार्य को 42 दिनों में कर सकते हैं |B और C ने एक साथ 21 दिनों तक कार्य किया और शेष कार्य A ने पूरा किया | पूरा कार्य कितने दिनों में समाप्त हुआ ?

A

99 days

B

102 days

C

96 days

D

93 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video & text solution for The ratio of efficiencies of A , B and C is 7 : 5 : 8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining was completed by A alone. The whole work was completed in : A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 8 है | एक साथ कार्य करते हुए, वे किसी कार्य को 42 दिनों में कर सकते हैं |B और C ने एक साथ 21 दिनों तक कार्य किया और शेष कार्य A ने पूरा किया | पूरा कार्य कितने दिनों में समाप्त हुआ ? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    The ratio of the efficiencies of A, B and C is 7:5:8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining work was completed by A alone. The whole work was completed in:

    A96 days
    B99 days
    C102 days
    DNone of these
  • Question 2 - Select One

    The ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?

    A18 days
    B24 days
    C21 days
    D15 days
  • Question 3 - Select One

    The efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in:

    A30 days
    B32 days
    C36 days
    D40 days