A can do a work in 40 days, B can do the same work in 60 days and C can do the same work in 80 days. They all together started the work and A left 11 days before also B left 8 days before the completion of whole task, find the number of days taken to complete the work.
A)13 days
B)26 days
C)39 days
D)52 days
The correct Answer is:B
To solve the problem step by step, let's break it down:
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 40 days, so A's work per day = 140 of the work.
- B can complete the work in 60 days, so B's work per day = 160 of the work.
- C can complete the work in 80 days, so C's work per day = 180 of the work.
Step 2: Find the Least Common Multiple (LCM) to express total work in units.
- The LCM of 40, 60, and 80 is 240.
- Thus, we can assume the total work is 240 units.
Step 3: Calculate the efficiency of A, B, and C in units.
- A's efficiency = 24040=6 units/day
- B's efficiency = 24060=4 units/day
- C's efficiency = 24080=3 units/day
Step 4: Calculate the total efficiency when all three are working together.
- Total efficiency = A's efficiency + B's efficiency + C's efficiency = 6+4+3=13 units/day.
Step 5: Determine how many days A and B worked.
- Let x be the total number of days taken to complete the work.
- A left 11 days before completion, so A worked for x−11 days.
- B left 8 days before completion, so B worked for x−8 days.
- C worked for the entire duration, x days.
Step 6: Set up the equation based on the work done.
- Work done by A = 6(x−11)
- Work done by B = 4(x−8)
- Work done by C = 3x
The total work done by A, B, and C should equal the total work (240 units):
6(x−11)+4(x−8)+3x=240
Step 7: Simplify the equation.
Expanding the equation:
6x−66+4x−32+3x=240
Combine like terms:
(6x+4x+3x)−98=240
13x−98=240
Step 8: Solve for x.
Add 98 to both sides:
13x=240+98
13x=338
Now divide by 13:
x=33813=26
Conclusion:
The total number of days taken to complete the work is 26 days.
---
- A can complete the work in 40 days, so A's work per day = 140 of the work.
- B can complete the work in 60 days, so B's work per day = 160 of the work.
- C can complete the work in 80 days, so C's work per day = 180 of the work.
- The LCM of 40, 60, and 80 is 240.
- Thus, we can assume the total work is 240 units.
- A's efficiency = 24040=6 units/day
- B's efficiency = 24060=4 units/day
- C's efficiency = 24080=3 units/day
- Total efficiency = A's efficiency + B's efficiency + C's efficiency = 6+4+3=13 units/day.
- Let x be the total number of days taken to complete the work.
- A left 11 days before completion, so A worked for x−11 days.
- B left 8 days before completion, so B worked for x−8 days.
- C worked for the entire duration, x days.
- Work done by A = 6(x−11)
- Work done by B = 4(x−8)
- Work done by C = 3x
6(x−11)+4(x−8)+3x=240
Expanding the equation:
6x−66+4x−32+3x=240
Combine like terms:
(6x+4x+3x)−98=240
13x−98=240
Add 98 to both sides:
13x=240+98
13x=338
Now divide by 13:
x=33813=26
The total number of days taken to complete the work is 26 days.
Similar Questions
A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View Solution
Knowledge Check
A can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?
A12B10C15D24A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is
A5 daysB10 daysC15 daysD20 daysIf P can do a work in 6 days and Q Can do the same work in
8 days. R can do the same work in 12 days. If they are
woeking together then the work will be completed in how
many days?A73daysB83daysC103daysD113days
If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.
View SolutionA can do a work in 4 days while B can do that same work in 6 days. If they worked together, then that work would be completed in
View SolutionA can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
View Solution