A can do a work in 40 days, B can do the same work in 60 days and C can do the same work in 80 days. They all together started the work and A left 11 days before also B left 8 days before the completion of whole task, find the number of days taken to complete the work.

A

A)13 days

B

B)26 days

C

C)39 days

D

D)52 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, let's break it down:

Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 40 days, so A's work per day = 140 of the work.
- B can complete the work in 60 days, so B's work per day = 160 of the work.
- C can complete the work in 80 days, so C's work per day = 180 of the work.

Step 2: Find the Least Common Multiple (LCM) to express total work in units.
- The LCM of 40, 60, and 80 is 240.
- Thus, we can assume the total work is 240 units.

Step 3: Calculate the efficiency of A, B, and C in units.
- A's efficiency = 24040=6 units/day
- B's efficiency = 24060=4 units/day
- C's efficiency = 24080=3 units/day

Step 4: Calculate the total efficiency when all three are working together.
- Total efficiency = A's efficiency + B's efficiency + C's efficiency = 6+4+3=13 units/day.

Step 5: Determine how many days A and B worked.
- Let x be the total number of days taken to complete the work.
- A left 11 days before completion, so A worked for x11 days.
- B left 8 days before completion, so B worked for x8 days.
- C worked for the entire duration, x days.

Step 6: Set up the equation based on the work done.
- Work done by A = 6(x11)
- Work done by B = 4(x8)
- Work done by C = 3x

The total work done by A, B, and C should equal the total work (240 units):
6(x11)+4(x8)+3x=240

Step 7: Simplify the equation.
Expanding the equation:
6x66+4x32+3x=240
Combine like terms:
(6x+4x+3x)98=240
13x98=240

Step 8: Solve for x.
Add 98 to both sides:
13x=240+98
13x=338
Now divide by 13:
x=33813=26

Conclusion:
The total number of days taken to complete the work is 26 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?

    A12
    B10
    C15
    D24
  • A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is

    A5 days
    B10 days
    C15 days
    D20 days
  • If P can do a work in 6 days and Q Can do the same work in
    8 days. R can do the same work in 12 days. If they are
    woeking together then the work will be completed in how
    many days?

    A73days
    B83days
    C103days
    D113days