A and B can do a work in 15 days and 10 days respectively. They started working together but after 2 days for some reason B had to leave the work and A alone did the remaining work. In how many days total work was finished?
A तथा B किसी कार्य को पूरा करने में क्रमशः 15 दिन तथा 10 दिन का समय लेते है। उन्होनें मिलकर कार्य करना आरंभ किया किंतु 2 दिन पश्चात किसी कारणवश B को कार्य छोड़ना पड़ा तथा शेष कार्य अकेले A ने पूरा किया। संपूर्ण कार्य कितने समय में पूरा हुआ?
10 days/10 दिन
8 days/8 दिन
12 days/12 दिन
15 days/15 दिन
The correct Answer is:C
To solve the problem, we need to determine how long it takes for A and B to complete the work together and then how long A takes to finish the remaining work after B leaves.
1. Determine the work rates of A and B:
- A can complete the work in 15 days. Therefore, A's work rate is 115 of the work per day.
- B can complete the work in 10 days. Therefore, B's work rate is 110 of the work per day.
2. Calculate the combined work rate of A and B:
- Combined work rate of A and B = A's work rate + B's work rate
Combined work rate=115+110
- To add these fractions, we need a common denominator. The least common multiple of 15 and 10 is 30.
115=230,110=330
- Therefore,
Combined work rate=230+330=530=16
- This means together, A and B can complete 16 of the work in one day.
3. Calculate the work done in the first 2 days:
- In 2 days, the amount of work completed by A and B together is:
Work done in 2 days=2×16=26=13
4. Determine the remaining work:
- Since 13 of the work is done, the remaining work is:
Remaining work=1−13=23
5. Calculate how long it takes A to finish the remaining work:
- A's work rate is 115 of the work per day. To find out how many days A needs to complete 23 of the work:
Days required by A=Remaining workA's work rate=23115=23×15=10 days
6. Calculate the total time taken to complete the work:
- Total time = Time worked together + Time taken by A alone
Total time=2 days+10 days=12 days
Final Answer:
The total work was finished in 12 days.
- A can complete the work in 15 days. Therefore, A's work rate is 115 of the work per day.
- B can complete the work in 10 days. Therefore, B's work rate is 110 of the work per day.
- Combined work rate of A and B = A's work rate + B's work rate
Combined work rate=115+110
- To add these fractions, we need a common denominator. The least common multiple of 15 and 10 is 30.
115=230,110=330
- Therefore,
Combined work rate=230+330=530=16
- This means together, A and B can complete 16 of the work in one day.
- In 2 days, the amount of work completed by A and B together is:
Work done in 2 days=2×16=26=13
- Since 13 of the work is done, the remaining work is:
Remaining work=1−13=23
- A's work rate is 115 of the work per day. To find out how many days A needs to complete 23 of the work:
Days required by A=Remaining workA's work rate=23115=23×15=10 days
- Total time = Time worked together + Time taken by A alone
Total time=2 days+10 days=12 days
The total work was finished in 12 days.
Similar Questions
A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View Solution
Knowledge Check
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:
A10 daysB8 daysC12 daysD15 daysRam and Mohan can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days Mohan had to leave and Ram alone completed the remaining work The whole work was completed in:
A5 daysB6 daysC10 daysD1012A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?
A203 daysB253 daysC6 daysD5 days
A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
View SolutionA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
View Solution