A and B can do a work in 15 days and 10 days respectively. They begin the work together but B leaves after two days. Now A completes the remaining work. The total number of days needed for the completion of the work is:

A

15 days

B

18 days

C

12 days

D

10 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video & text solution for A and B can do a work in 15 days and 10 days respectively. They begin the work together but B leaves after two days. Now A completes the remaining work. The total number of days needed for the completion of the work is: by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

    A2 days
    B3 days
    C1 day
    DNone of these
  • Question 2 - Select One

    A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:

    A10 days
    B8 days
    C12 days
    D15 days
  • Question 3 - Select One

    A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?

    A1425 days
    B9days
    C8days
    D759 days