Pavan is thrice as efficient as koushik. Pavan alone takes 30 days to complete a work. In how many days can koushik finish the same work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:=90


To solve the problem, let's break it down step by step.

Step 1: Understand the efficiency relationship
Pavan is thrice as efficient as Koushik. This means that if Koushik's efficiency is represented as 1 unit of work per day, then Pavan's efficiency would be 3 units of work per day.

Step 2: Determine Pavan's work rate
Pavan alone takes 30 days to complete the work. Therefore, the total work can be calculated as:
Total Work=Work Rate×Time
Since Pavan's work rate is 3 units of work per day, the total work is:
Total Work=3 units/day×30 days=90 units

Step 3: Calculate Koushik's work rate
Since Koushik is less efficient, we know that his efficiency is 1 unit of work per day.

Step 4: Calculate the time taken by Koushik to complete the work
Now, we need to find out how many days Koushik would take to complete the same total work of 90 units. We can use the formula:
Time=Total WorkWork Rate
Substituting the values we have:
Time=90 units1 unit/day=90 days

Conclusion
Koushik can finish the same work in 90 days.

---

Updated on:18/9/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Nikhil is twice as efficient as Anil Nikhil takes 30 days to complete the work alone, in how many days can Anil finish the work?

    A60 days
    B30 days
    C20 days
    D40 days
  • Nikhil is twice as efficient as Anil Nikhil takes 30 days to complete the work alone, in how many days can Anil finish the work?

    A60 days
    B30 days
    C20 days
    D40 days
  • M is thrice as good as workman as N and together they finish a piece of work in 30 days. In how many days will M alone finish the work?

    A50
    B40
    C60
    D45