A can complete a work in 12 days, B in 15 days. Find the time taken by them: when A and B worked alternatively started by B.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem of how long A and B will take to complete the work when they work alternately starting with B, we can follow these steps:

Step 1: Determine the work done by A and B in one day.
- A can complete the work in 12 days. Therefore, A's work rate is:
Work rate of A=1 work12 days=5 units1 day

- B can complete the work in 15 days. Therefore, B's work rate is:
Work rate of B=1 work15 days=4 units1 day

Step 2: Calculate the total work done in 2 days.
- In the first day, B works and completes 4 units.
- In the second day, A works and completes 5 units.
- Therefore, the total work done in 2 days is:
Total work in 2 days=4 units+5 units=9 units

Step 3: Determine how many complete cycles of 2 days are needed to finish the work.
- Let’s assume the total work is 60 units (as a common multiple of A's and B's work rates).
- To find out how many complete cycles of 2 days are needed to reach close to 60 units:
Number of complete cycles=60 units9 units per 2 days=6.67 cycles
This means they can complete 6 full cycles of 2 days (which equals 12 days) and then some additional work.

Step 4: Calculate the work done in 12 days.
- In 12 days (6 cycles), the total work done is:
Total work done in 12 days=6×9=54 units

Step 5: Calculate the remaining work.
- The remaining work after 12 days is:
Remaining work=60 units54 units=6 units

Step 6: Determine who works next and how much time it takes to finish the remaining work.
- On the 13th day, B will work again and can complete 4 units.
- After B works on the 13th day, the remaining work will be:
Remaining work after 13th day=6 units4 units=2 units

Step 7: Calculate the time taken by A to finish the remaining work.
- On the 14th day, A will work and can complete 5 units in 1 day.
- To complete the remaining 2 units, A will take:
Time taken by A=2 units5 units per day=25 days

Step 8: Calculate the total time taken.
- The total time taken is:
Total time=12 days+1 day+25 days=13+25=675 days=1325 days

Final Answer:
A and B will take 13 2/5 days to complete the work when they work alternately starting with B.

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.

    A8 days
    B10 days
    C6 days
    D9 days
  • A and B can complete a work in 12 days and 18 days, respectively. A begins to do the work and they work alternately one at a time for 1 day each. The whole work will be completed in how many days?

    A1423
    B1413
    C1425
    D1457