A work can be completed by P and Q in 12 days, Q and R in 15 days, Rand P in 20 days. In how many days P alone can finish the work?

A

10

B

20

C

30

D

60

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first determine the work rates of P, Q, and R based on the information given.

Step 1: Define the work rates
Let the work done by P in one day be P, by Q be Q, and by R be R.

From the problem, we have:
1. P and Q together can complete the work in 12 days:
P+Q=112(1)
2. Q and R together can complete the work in 15 days:
Q+R=115(2)
3. R and P together can complete the work in 20 days:
R+P=120(3)

Step 2: Add the equations
Now, we will add equations (1), (2), and (3):
(P+Q)+(Q+R)+(R+P)=112+115+120
This simplifies to:
2P+2Q+2R=112+115+120

Step 3: Find a common denominator
To add the fractions on the right side, we need a common denominator. The least common multiple of 12, 15, and 20 is 60.

Converting each fraction:
112=560,115=460,120=360
Adding these gives:
560+460+360=1260=15

Step 4: Simplify the equation
Now we substitute back into our equation:
2P+2Q+2R=15
Dividing everything by 2:
P+Q+R=110(4)

Step 5: Isolate P
Now we can find P by using equation (4) and one of the previous equations. Let's use equation (2) to isolate P:
P=(P+Q+R)(Q+R)
Substituting from (4) and (2):
P=110115

Step 6: Find a common denominator for P
The common denominator for 10 and 15 is 30:
110=330,115=230
So,
P=330230=130

Step 7: Calculate the days P alone can finish the work
Since P represents the work done by P in one day, if P=130, it means P can complete the work alone in 30 days.

Final Answer:
P alone can finish the work in 30 days.

---

|
Updated on:7/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A work can be completed by P and Q in 12 days, and R in 15 days, R and P in 20 days. In how many days P alone can finish the work?

    A10 days
    B20 days
    C30 days
    D60 days
  • Question 2 - Select One

    A and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?

    A56 days
    B48 days
    C36 days
    D64 days
  • Question 3 - Select One

    A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?

    A7days
    B712 days
    C8 days
    D812days