A work can be completed by P and Q in 12 days, Q and R in 15 days, Rand P in 20 days. In how many days P alone can finish the work?
10
20
30
60
The correct Answer is:C
To solve the problem step by step, we will first determine the work rates of P, Q, and R based on the information given.
Step 1: Define the work rates
Let the work done by P in one day be P, by Q be Q, and by R be R.
From the problem, we have:
1. P and Q together can complete the work in 12 days:
P+Q=112(1)
2. Q and R together can complete the work in 15 days:
Q+R=115(2)
3. R and P together can complete the work in 20 days:
R+P=120(3)
Step 2: Add the equations
Now, we will add equations (1), (2), and (3):
(P+Q)+(Q+R)+(R+P)=112+115+120
This simplifies to:
2P+2Q+2R=112+115+120
Step 3: Find a common denominator
To add the fractions on the right side, we need a common denominator. The least common multiple of 12, 15, and 20 is 60.
Converting each fraction:
112=560,115=460,120=360
Adding these gives:
560+460+360=1260=15
Step 4: Simplify the equation
Now we substitute back into our equation:
2P+2Q+2R=15
Dividing everything by 2:
P+Q+R=110(4)
Step 5: Isolate P
Now we can find P by using equation (4) and one of the previous equations. Let's use equation (2) to isolate P:
P=(P+Q+R)−(Q+R)
Substituting from (4) and (2):
P=110−115
Step 6: Find a common denominator for P
The common denominator for 10 and 15 is 30:
110=330,115=230
So,
P=330−230=130
Step 7: Calculate the days P alone can finish the work
Since P represents the work done by P in one day, if P=130, it means P can complete the work alone in 30 days.
Final Answer:
P alone can finish the work in 30 days.
---
Let the work done by P in one day be P, by Q be Q, and by R be R.
1. P and Q together can complete the work in 12 days:
P+Q=112(1)
2. Q and R together can complete the work in 15 days:
Q+R=115(2)
3. R and P together can complete the work in 20 days:
R+P=120(3)
Now, we will add equations (1), (2), and (3):
(P+Q)+(Q+R)+(R+P)=112+115+120
This simplifies to:
2P+2Q+2R=112+115+120
To add the fractions on the right side, we need a common denominator. The least common multiple of 12, 15, and 20 is 60.
112=560,115=460,120=360
Adding these gives:
560+460+360=1260=15
Now we substitute back into our equation:
2P+2Q+2R=15
Dividing everything by 2:
P+Q+R=110(4)
Now we can find P by using equation (4) and one of the previous equations. Let's use equation (2) to isolate P:
P=(P+Q+R)−(Q+R)
Substituting from (4) and (2):
P=110−115
The common denominator for 10 and 15 is 30:
110=330,115=230
So,
P=330−230=130
Since P represents the work done by P in one day, if P=130, it means P can complete the work alone in 30 days.
P alone can finish the work in 30 days.
Similar Questions
A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. In how many days can A alone finish the work?
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View Solution
Knowledge Check
- Question 1 - Select One
A work can be completed by P and Q in 12 days, and R in 15 days, R and P in 20 days. In how many days P alone can finish the work?
A10 daysB20 daysC30 daysD60 days - Question 2 - Select One
A and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?
A56 daysB48 daysC36 daysD64 days - Question 3 - Select One
A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?
A7daysB712 daysC8 daysD812days
P can do a piece of work in 15 days and Q in 20 days. With help of R, they finish the work in 5 days. In how many days R alone can do the same work?
View SolutionA can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
View SolutionA and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionA can do a piece of work in 12 days and B in 15 days. With help of C, they finish the work in 4 days. In how many days C alone can do the same work?
View Solution