A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
100
110
55
50
The correct Answer is:B
To solve the problem step by step, we can follow these instructions:
Step 1: Define the variables
Let the original number of workers be X.
Step 2: Set up the equation for the work done
If X workers can complete the work in 100 days, then the total work can be expressed in terms of worker-days:
Total Work=X×100
Step 3: Set up the equation for the work done with fewer workers
If 10 workers are absent, then the number of workers becomes X−10. These workers complete the same amount of work in 110 days:
Total Work=(X−10)×110
Step 4: Set the two expressions for total work equal to each other
Since both expressions represent the same total work, we can set them equal:
X×100=(X−10)×110
Step 5: Expand and simplify the equation
Expanding the right side:
100X=110X−1100
Step 6: Rearrange the equation to isolate X
Now, let's move all terms involving X to one side and the constant to the other side:
100X−110X=−1100
−10X=−1100
Step 7: Solve for X
Dividing both sides by -10 gives:
X=110010=110
Conclusion
The original number of workers was 110.
---
Let the original number of workers be X.
If X workers can complete the work in 100 days, then the total work can be expressed in terms of worker-days:
Total Work=X×100
If 10 workers are absent, then the number of workers becomes X−10. These workers complete the same amount of work in 110 days:
Total Work=(X−10)×110
Since both expressions represent the same total work, we can set them equal:
X×100=(X−10)×110
Expanding the right side:
100X=110X−1100
Now, let's move all terms involving X to one side and the constant to the other side:
100X−110X=−1100
−10X=−1100
Dividing both sides by -10 gives:
X=110010=110
The original number of workers was 110.
Similar Questions
Knowledge Check
A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
A100B110C55D50A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?
Aa. 10%Bb. 1427%Cc. 20%Dd. can't be determinedA Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?
A10%B1427%C20%Dcan’t be determined
A group of workers can complete a job in 120 days. If there were 4 more such workers then the work could be finished in 12 days less. What was the actual strength of workers?
View SolutionHow many workers are required for completing the construction work in the 10 days ?
(i) 20% of the work can be completed by 8 workers in 8 days.
(ii) 20 workers can complete the work in 16 days.
(iii) One - eighth of the work can ve completed by 8 workers in 5 days.
View Solution42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
View Solution56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
View Solution30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days if all the 30 workers started the work.
View Solution